Happy Easter!
I know it's been more than a week since I've updated Remodeling 1070. Work was being done, but most of it was difficult to photograph. I wanted to wait to add another post until I had some photos to share.
At the end of Week 8 - has it really been 2 months already? - the master suite has walls double coated with primer, the paint has been chosen, and the sliding pocket doors have been installed (see the photos below). It's looking more and more like a real group of rooms with each passing day.
Week 9 will be pretty exciting, as the bathroom tile and cabinet work will begin. And since the tile installation team is the same team that does the glass block, we should have the glass block in the second closet and master bath soon as well. We are very excited at the thought of actually having windows in place again!
Enjoy the photos below, and most of all, have a terrific Easter weekend.